End-to-end flow
JT122579 · Aldeakva
One inquiry, all stages. Each box below is the actual artifact persisted by the pipeline — not a mockup. The brief asks: "does Kine actually work?". This page is the answer.
9 stages
- From: erling@aldeakva.noSubject: Forespørsel ventiler avløpskum Blom SettefiskBody: 1229 charsAttachments: 6017-DOK-100-Tilbudsforespørsel skyvespjeldventiler.pdf, IMG_2346.jpeg, Outlook-Image.png, image240566.gif
Show full email body
You don't often get email from erling@aldeakva.no. Learn why this is important<https://aka.ms/LearnAboutSenderIdentification> Hei Henrik! Vi holder på med et prosjekt for Blom Settefisk på Askøy og har i den forbindelse behov for noen ventiler til en avløpskum. Fant disse i et magasin fra dere og tar derfor kontakt med en forespørsel, se vedlegg. Takk for svar!🙂 [Image] Vennlig hilsen Erling Mikalsen Rådgiver akvakultur B.Sc Havbruksingeniør M.Sc Ledelse av teknologi Mobil : 98 42 52 24 Epost: erling@aldeakva.no<mailto:erling@aldeakva.no> Vabakkjen 6, 5411 Stord www.aldeakva.no<https://mibc-fr-06.mailinblack.com/securelink/?url=http://www.aldeakva.no&key=eyJsYW5nIjoiRU4iLCJ1cmwiOiJodHRwOi8vd3d3LmFsZGVha3ZhLm5vLyIsInRva2VuIjoiZ0FBQUFBQnBROW1VbzdLdHMya3dfQzA0cnY3Yk1aRTliLUtIaUlQSGlzbFc1LXdwallIUm1lOVNMQTlDdnNPWGpma3V6czJ1T0RmX0lDR1o2SVFLZFZZY3k5b19aYUVsc3FGUVhoczlOUGlnYWo0Z294WUMxOW1MQ2pLeGRneFkzMGswLWJtZnNsTldzVHhxN0h2eWJLY3QwZUNMeHlyb3JVc1VIX3Q4MFYyRzBmd2Jwejg3UWt2VjNNT3d0d3lDalE3SktBalhvUkYyTVA4WGxIeERqcnVld1NYUUNrMnFRQmZ0Tmk5NHNxREVCamhJbVp2Zk54RUFxYzBhWUhTWlRJVnVmLVNRUEtsbGtvb21xeXZHTC1uY1c2cTB5dTJoV0NvSC1VQmJCQW5BODBkdElkcUM3czQ1b0tMTGZKeTBvNnQ4am16cjAyWVEifQ==>
Show extracted JSON
{ "language": "no", "intent": "new_inquiry", "customer": { "company": "Aldeakva", "contact_name": "Erling Mikalsen", "contact_email": "erling@aldeakva.no", "phone": "+47 98 42 52 24", "vat_number": null, "address": "Vabakkjen 6, 5411 Stord, Norway" }, "items": [ { "line_no": 1, "quantity": null, "unit": null, "product_reference": "Valves for a drainage well (avløpskum) at Blom Settefisk fish farm on Askøy — found in JS Cock magazine, full spec in attachment", "manufacturer": null, "manufacturer_part_no": null, "cross_ref_to": null, "specs": { "dimension": null, "pressure_rating": null, "material_body": null, "material_seal": null, "actuation": null, "voltage": null, "torque_or_flow": null, "temperature": null, "thread_or_connection": null, "other": [ { "key": "application", "value": "avløpskum (drainage well)" }, { "key": "site", "value": "Blom Settefisk, Askøy" }, { "key": "discovery_source", "value": "JS Cock product magazine" } ] }, "missing_fields": [ "all specs — in the attachment" ] } ], "application_context": "Aquaculture project for Blom Settefisk fish farm on Askøy. Customer found suitable valves in JS Cock's magazine and asks for an offer per attachment.", "attachments_referenced": [ "valve spec attachment (filename not in body)" ], "delivery": { "location": "Blom Settefisk, Askøy", "deadline": null, "incoterms": null }, "previous_reference": { "is_update_of": null, "notes": null }, "completeness": "partial", "missing": [ "item specs (in attachment)", "quantities", "deadline" ] }- partial
- item specs (in attachment)
- quantities
- deadline
Rule trace (deterministic)Verdict: partial · 1 of 1 items need clarification- item 1: × needs follow-up — no quantity
- Subject: Re: Ventilspørsmål for Blom Settefisk, Askøy
Hei Erling, Takk for forespørselen om ventiler til avløpskummen på Blom Settefisk! Vi har mottatt din henvendelse og vil gjerne hjelpe. For å gi dere et nøyaktig tilbud, trenger vi bare noen få opplysninger: • Komplette spesifikasjoner for ventilene (type, størrelse, trykklasse, osv.) • Mengde ventiler som trengs • Ønsket leveringsfrist Når vi får disse detaljene, sender vi dere et tilbud raskt. Med vennlig hilsen J.S.Cock A/S sales team
Drafted by haiku · awaiting human approval. - BC#: C-20005Company: AldeakvaEmail: erling@aldeakva.no
- 6ok
Match items against the J.S.Cock catalog
Steps 12 + 13Top-5 candidates per item via TF-IDF over 18.8k SKUs (see Matches tab on /inquiry/JT122579).
- 7skip
Score supplier quotes
Steps 16 + 17No supplier replies received yet — scoring waits for at least one.
- 8skip
Draft quote in Business Central
Steps 10 + 20Waiting for the supplier quote to land before drafting.
- 9pending
Human approval (sales engineer)
Step 21In production this becomes a real review UI in Week 2-3. Demo: approve / edit / reject from the page.
Process map: see how this aligns with JS Cock’s diagram →