JT123218 · Litus Akva
One inquiry, all stages. Each box below is the actual artifact persisted by the pipeline — not a mockup. The brief asks: "does Kine actually work?". This page is the answer.
9 stages
- From: nicolai@litus-akva.noSubject: Tilbud eltrisk aktuatorstyrt membarnventilBody: 1166 charsAttachments: image001.png, image003.png, image750346.gif
Show full email body
You don't often get email from nicolai@litus-akva.no<mailto:nicolai@litus-akva.no>. Learn why this is important<https://aka.ms/LearnAboutSenderIdentification> Hei, Kan vi få et tilbud av dere på 4 stk. elektriske aktuatorstyrte membranventiler i materialet PDVF/PP i rørdimensjon DN50, med reguleringsmuligheter? Vennlig hilsen Nicolai Dypevik Site Manager | T: 484 00 705 | E: nicolai@litus-akva.no<mailto:nicolai@litus-akva.no> | w: litusakva.com<mailto:www.litusakva.com> [cid:image003.png@01DC99AC.4A942640] https://www.litusakva.com/<https://mibc-fr-06.mailinblack.com/securelink/?url=https://www.litusakva.com&key=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>
Show extracted JSON
{ "language": "no", "intent": "new_inquiry", "customer": { "company": "Litus Akva", "contact_name": "Nicolai Dypevik", "contact_email": "nicolai@litus-akva.no", "phone": "484 00 705", "vat_number": null, "address": null }, "items": [ { "line_no": 1, "quantity": 4, "unit": "stk", "product_reference": "Elektriske aktuatorstyrte membranventiler (Electrically actuated diaphragm valves)", "manufacturer": null, "manufacturer_part_no": null, "cross_ref_to": null, "specs": { "dimension": "DN50", "pressure_rating": null, "material_body": "PDVF", "material_seal": "PP", "actuation": "electric", "voltage": null, "torque_or_flow": null, "temperature": null, "thread_or_connection": null, "other": [ { "key": "regulation_capability", "value": "requested" } ] }, "missing_fields": [ "pressure_rating", "voltage", "thread_or_connection", "temperature", "torque_or_flow", "manufacturer" ] } ], "application_context": null, "attachments_referenced": [], "delivery": { "location": null, "deadline": null, "incoterms": null }, "previous_reference": { "is_update_of": null, "notes": null }, "completeness": "partial", "missing": [ "application_context", "pressure_rating", "voltage", "thread_or_connection", "temperature" ] }- 3ok
Completeness verdict: partial
Step 03Missing: application_context, pressure_rating, voltage, thread_or_connection, temperature
partial- application_context
- pressure_rating
- voltage
- thread_or_connection
- temperature
Rule trace (deterministic)Verdict: complete · all items quotable directly- item 1: ✓ quotable — quotable (sizing + 3 disambiguating specs)
- Subject: Re: Tilbud på elektriske aktuatorstyrte membranventiler DN50
Hei Nicolai, Takk for forespørselen om 4 elektriske aktuatorstyrte membranventiler i PDVF/PP, DN50! For å kunne gi deg et presist tilbud, trenger vi noen detaljer til: - Trykkvurdering (bar/MPa) - Stemmespanning og type (AC/DC) - Temperaturområde for mediet - Gjenger- eller koblingstype (flansche, tråd, etc.) - Reguleringstype eller gjennomstrøming (Cv/Kv-verdi) Når vi får disse opplysningene, sender vi deg tilbud raskt. Med vennlig hilsen, J.S.Cock A/S sales team
Drafted by haiku · awaiting human approval. - BC#: C-20039Company: Litus AkvaEmail: nicolai@litus-akva.no
- 6ok
Match items against the J.S.Cock catalog
Steps 12 + 13Top-5 candidates per item via TF-IDF over 18.8k SKUs (see Matches tab on /inquiry/JT123218).
- 7skip
Score supplier quotes
Steps 16 + 17No supplier replies received yet — scoring waits for at least one.
- 8skip
Draft quote in Business Central
Steps 10 + 20Waiting for the supplier quote to land before drafting.
- 9pending
Human approval (sales engineer)
Step 21In production this becomes a real review UI in Week 2-3. Demo: approve / edit / reject from the page.